Completion of the repair works on the track no. 1 of Henri Coanda Airport

0 1.175

The Bucharest National Airports Company completed, on Monday, the 21 November, the 24.00 time, the repair works on the road structure of the take-off / landing runway no. 1 a Henri Coandă Bucharest International Airport.

lucrari-pista1-otp-3

Repairs to the track no. 1 of Henri Coanda Airport

The works were realized in a record time, of only 35 days, and totaled an area of ​​42.945 sqm, of which 40.820 sqm at track nr 1 (08R-26L) and other 2.125 sqm on one of the tracks.

The works had a high degree of complexity and were carried out at a sustained pace, depending on the weather conditions (rain, low visibility, low temperatures), the absolute priority of the Bucharest Airports National Company being the safe operation of air traffic at Henri Coandă Airport. .

The completion of the works allows the operation of the track no. 1 at maximum capacity, including in low visibility conditions (fog, heavy snowfall) or adverse weather.

Bucharest National Airport Company has taken all the necessary measures for the complete safety and security of the airport activities and for the comfort of the passengers passing through Henri Coanda Airport.