Repair works on the track no. 1 of Henri Coanda Airport

The Bucharest Airports National Company has started this month the repair works on the road structure of the take-off / landing runway no. 1 (08R / 26L) of Henri Coandă Bucharest International Airport.

0 927

For the safe and secure conduct of the airport activities, as well as to minimize the discomfort of the passengers, the repair work will be performed within the 16.00 - 06.00 time interval.

1-works-track-airport Otopeni

Repair works on the track no. 1

Every night 1.500 - 1.700 sqm is completed, the works consisting of milling the existing asphalt mixes, on a thickness of 10 cm and the release of two new layers of asphalt mixes.

The current repairs have a high degree of complexity and run at a sustained pace until the completion of the works, which will total 38.000 sqm.

In the second quarter of this year, works were performed on the surface of the movement consisting of asphalt carpet siding on rolling paths and platforms, totaling 22.500 sqm.

Also, this year, concrete slabs were replaced on the treads and platforms, over a total area of ​​over 5.200 sqm.