The modernization of the airport in Sibiu is in a straight line. The financing contract for the new terminal has been signed.

0 719

The modernization of the airport in Sibiu is in a straight line. The financing contract was signed on Friday, 17.06.2022, at the headquarters of the Ministry of Transport and Infrastructure, and on 22.06.2022, at the headquarters of the Sibiu County Council, was signed the contract for design and execution of works for the objective "Modernization and development of airport infrastructure - activities economic ”, Phase I. The total value of the project is 272.493.421,67 lei.

Modernization of the airport in Sibiu

The terminal will have a built area of ​​22.400 square meters, with a total processing capacity of approximately 2,5 million passengers, 6 security filters, 7 vending machines for self-check-in, 10 check-in counters with operator, one of which serves VIP flow, 7 boarding gates, as well as other facilities necessary for international and extra-community international air traffic, plus public spaces for commercial and utilitarian use.

The project will be carried out by the association of three strong companies with extensive experience:

  • ✅ CON-A SRL [LEADER]
  • ✅ BOG'Art SRL [ASSOCIATE]
  • ✅ UTI CONSTRUCTION AND FACILITY MANAGEMENT SA [ASSOCIATED]

The deadline for completion of construction is December 31, 2023

"It is certainly one of the most important steps in terms of modernization and development of airport infrastructure. Basically, it is the culmination of a team work of more than three years between the ministry, the designer, the airport management team and the team of specialists of the Sibiu County Council. The ultimate goal is to ensure an infrastructure that meets all future challenges both in terms of increasing passenger traffic and the level of services provided to passengers and other categories of customers, so that their experience is at the level of their expectations. There is a period of challenges ahead, in principle due to the scale of this project, but we are confident that the project will be a successful one through constant and intensive collaboration from all parties involved. ” - said Marius Ioan GÎRDEA, General Manager of Sibiu International Airport